Cookies

We use essential cookies to make our site work. We'd also like to set analytics cookies that help us make improvements by measuring how you use the site. These will be set only if you accept.

For more detailed information about the cookies we use, see our cookies page.

Essential Cookies

Essential cookies enable core functionality such as security, network management, and accessibility. For example, the selections you make here about which cookies to accept are stored in a cookie.

You may disable these by changing your browser settings, but this may affect how the website functions.

Analytics Cookies

We'd like to set Google Analytics cookies to help us improve our website by collecting and reporting information on how you use it. The cookies collect information in a way that does not directly identify you.

Third Party Cookies

Third party cookies are ones planted by other websites while using this site. This may occur (for example) where a Twitter or Facebook feed is embedded with a page. Selecting to turn these off will hide such content.

Skip to main content

The DITCH PROJECT 22/23

UPDATE 9 APRIL 2023

The work to replace ditches, Banks and level the edge of the green is now largely complete, Hooray!!

As outlined below Club volunteers undertook lots of preparatory work before the contractors came on site early in 2023.  The contractors levelled around the edge of the green, installed the new concrete ditch profiles, covered the banks with artificial grass, levelled the edge of the green and finally laid new quality turf around the green edges.

When the contractors left volunteers could return to the green.  Jobs undertaken included backfill the gap between the new ditch profiles and the existing slabs surrounding the green.  In mid March we were able to undertake the first cut of the new turf, we have slowly reduced the height of cut, but it is likely be the middle of May before the new turf can be reduced to normal  season playing length.

Ashley completed adjustment of the metal steps to suit the new banks etc.  Boxing has been prepared to surround the irrigation sprinkler heads ( these were adjusted to suit the height of the new banks and are new several inches above the existing slabs)  These should make the surrounds safe to use although all players will need to take care when getting on and off the green. and preferably use the STEPS

The only significant work to be done are to mark out the green with 2 and 25 M markers and three sets of rinks to allow regular moving to ensure even wear on the green

Update ~Autumn 2022

At last this big project is underway. For many seasons our ditches have been collapsing and the grass edges of the green have been sloping down to the ditch. Stopping a bowl within a metre of the ditch has become virtually impossible. But from April 2023 this will be no more.

The fund raising has happened, options identified and on Monday 28th November the actual work began.

Message from project manager, Paul "As you will be aware from previous communications and the update at the recent Club AGM we are moving forward with the project to replace ditches, banks and level the outside edge of the green.  We need to undertake quite a lot of preparatory work (to save costs) before the contractor comes on site.  We need to remove the existing artificial grass etc from the banks, remove the concrete ditch profiles and lift some turf around the edge of the green."

Concrete ditches to be stacked ready for use as hardcore in future projects/refurbs. Good turf to be reused e.g.to fill patches on the green (e.g. clover removal) with poorer bits composted in new compost bins. 

Here is the onsite report on day one 29th November 2022(SS)

"The Ditch Project is underway. Lots of willing hands gathered at the green. Ralph had to carry out some rehoming of wildlife. Amazing what 65 plus year olds can do when playing bowls is the carrot! There was mist rising as time was called on an excellent effort by all those who turned up. Made me recall that old country saying….'Mist in the hollows good weather follows.' Well done everyone."

Onsite report 5th December 2022 (KB)

Today we saw the turf cutter clear approximately 1m of turf (and muddy bits) around the green. Turf then rolled where possible or lifted. Poorer bits filling the back of Oak Tree Corner and other points around the surrounds, better bits filling patches left by removal of clover on the green.  Sounds simple but was hard work done by a great team.  Final touches being done 6th December. 

Biddenden Bowls Club is very grateful to the bodies who have helped us complete this project by providing grants and loans. Also the members who came along to the green to carry out preparation, clear up and the making good work necessary. The club contributed a significant amount of the project costs plus 75+ volunteer hours.  Thanks go to  the following bodies for their support 

Kent Community Foundation - Grant 

Ashford Borough Council  - Grant

Biddenden Parish Council - Grant

Tractorfest - Grant

VHSC - payment from reserve

Bowls England - Loan